Bulgaria PV+Storage Project

Published on:2026-05-08

|

Posted by:SunLink

Application Scenario

Application Scenario

Source-side PV+storage plant - peak shaving

Independent PV-BESS Power Plant

Peak Shaving and Valley Filling

Project Location

Site Location

Bulgaria

Bulgaria

Installed Capacity

Installed Capacity

PV: 10MWp 

BESS: 10MW-20MWh

Plant Type

Project category

Ground-mounted PV + container-type storage plant

Ground Mounted PV and BESS Container Power Station

Annual PV generation

Annual Power Generation

12,000,000KWh

Daily storage cycles

Daily Cycle Number of Energy Storage

1

1 cycle/day

Storage Operating Mode

BESS Operation Mode

Grid-tied

Grid Connected

Emission Reduction

Emission Reduction

3880t/3880tons

Bulgaria grid emission factor0.324 kgCO₂/kWh

Average Grid Emission Factor of Bulgaria

0.324 kgCO₂/kWh

Power-Sales Model

Power Sales Mode

Full off-take by utility - storage-based peak shaving

Full Purchase by the Grid Company-BESS supports Peak Shaving and Valley Filling